Asante Gold commissions crusher at Bibiani - Mining Magazine

2022-10-11 04:04:06 By : Mr. YIFAN YIFAN

Meet the industry leaders who shape the Future of Mining in the Americas

location: Sofitel Sydney Wentworth, Australia

Meet the industry leaders who shape the Future of Mining in Australia

A review of the most digitalised operations on the planet, including analysis of...

An industry review of operations using autonomous solutions around the world, including...

A comprehensive review of current exploration rates, trending exploration technologies,...

The Mining Magazine Intelligence Future Fleets Report brings together the most forward-looking...

Inventory, WIP, Yield, and Recovery in heavy industry

Thermal management for the next generation of mining equipment shouldn't be ignored

Understand Project Gains Before You Implement

How Effective are Collision Awareness Systems in Surface Mines?

Liebherr to premiere hydrogen prototype engines Fleet 10 OCT 2022

Kumba faces force majeure due to strike Operational Excellence 10 OCT 2022

SHOCKWAVE blasts away start-up rivals Development 07 OCT 2022

Caterpillar adds technology packages for electric rope... Simulation / Optimisation 06 OCT 2022

BHP orders underground fleet from Normet Fleet 06 OCT 2022

Komatsu's next underground play Fleet 06 OCT 2022

Wärtsilä to upgrade Nevada Gold power plant Plant 05 OCT 2022

Metso Outotec wins SA platinum filter order Plant 05 OCT 2022

Pensana secures 25% offtake deal Plant 04 OCT 2022

Transparency critical in mining's 'perfect storm' Supply chain management 10 OCT 2022

Glencore to put German zinc smelter on C&M Maintenance 06 OCT 2022

Caterpillar adds technology packages for electric rope... Simulation / Optimisation 06 OCT 2022

Rio Tinto subsidiary inks renewable energy deal Power / Remote power 06 OCT 2022

Glencore to put German zinc smelter on C&M Maintenance 06 OCT 2022

Caterpillar adds technology packages for electric rope... Simulation / Optimisation 06 OCT 2022

Mapping firm studies rare species risk Sustainability 10 OCT 2022

Transparency critical in mining's 'perfect storm' Supply chain management 10 OCT 2022

Epiroc snaps up Geoscan Exploration 07 OCT 2022

Asante Gold installs a crusher at Bibiani.

Digitalising the way to net zero through collaboration

Integral solutions to improve your production strategies and productivity goals

Formula for success with Geographe

ABB on pillars for stronger digitalisation platforms

Asante Gold has completed the refurbishment of its primary crusher at the Bibiani gold mine in Ghana, and it is now operational.

The company anticipates its first gold pour in the September quarter this year.

Digitalising the way to net zero through collaboration

Integral solutions to improve your production strategies and productivity goals

Formula for success with Geographe

ABB on pillars for stronger digitalisation platforms

The Vancouver-based company will continue to stockpile ore for the next few weeks to support the imminent start of processing when the downstream process plant equipment is operational.

Ore stockpiling on the run of mine pad began in February.

The primary crusher system includes a 42-inch by 72-inch gyratory crusher which can provide 544 tonnes per hour to the mill.  

"Our refurbishment efforts at the Bibiani Gold Mine have been delivered ahead of schedule," Asante Gold chief executive Dave Anthony said.

Asante Gold relied on local contractors Kenmore Limited and Harlequin International for the crusher re-build, with Kenmore acting as lead contractor. Harlequin International was responsible for the refurbishment or replacement of all associated conveyors and control equipment.

The company had also acquired and installed a Knelson 6G concentrator and Gekko intensive leach reactor.

Asante Gold said in February it was planning to begin a preliminary economic assessment of an underground mine at Bibiani in the September quarter. This underground mine would be completed by 2026.

Digitalising the way to net zero through collaboration

Integral solutions to improve your production strategies and productivity goals

Formula for success with Geographe

ABB on pillars for stronger digitalisation platforms

Wärtsilä to upgrade Nevada Gold power plant

Metso Outotec wins SA platinum filter order

Euro Manganese produces manganese with Nano One process

Gold production is targeted for the September quarter.

Asante Gold ahead of schedule in processing plant refurb at Bibiani

Asante contracts PW Mining for Bibiani

Steppe Gold nears completion of new fixed crusher

TRX Gold commissions expanded mill at Buckreef

TRX Gold commissions expanded mill at Buckreef

Euro Manganese produces manganese with Nano One process

Learn about crushers, crushing stages and how to choose the right crusher

Built To Take A Beating. And Give One Right Back.

TENDER FOR THE EXPLOITATION OF THE BAUXITE BLOCK OF SANTOU (TELIMELE), GUINEA

Responding to the Needs of Customers Facing High Crushing Productivity Demands

How Continuous Surface Mining & Drill & Blast Can Work Together on the Same Mine

Download the new ABB eBook: Journey to autonomous mining

Revolutionize Tailings Management with the TDW Pump

Metso Outotec's bulk transportation solution

Proper Pump Clearance = Longer Wear Life

Learn about crushers, crushing stages and how to choose the right crusher

Built To Take A Beating. And Give One Right Back.

TENDER FOR THE EXPLOITATION OF THE BAUXITE BLOCK OF SANTOU (TELIMELE), GUINEA

Responding to the Needs of Customers Facing High Crushing Productivity Demands

How Continuous Surface Mining & Drill & Blast Can Work Together on the Same Mine

Download the new ABB eBook: Journey to autonomous mining

Revolutionize Tailings Management with the TDW Pump

Metso Outotec's bulk transportation solution

Proper Pump Clearance = Longer Wear Life

Wärtsilä to upgrade Nevada Gold power plant

Metso Outotec wins SA platinum filter order

Euro Manganese produces manganese with Nano One process

Copyright © 2000-2022 Aspermont Media Ltd. All rights reserved. Aspermont Media is a company registered in England and Wales. Company No. 08096447. VAT No. 136738101. Aspermont Media, WeWork, 1 Poultry, London, England, EC2R 8EJ.